Our upcoming maintenance project to improve roadway aesthetics by sealcoating and parking stall restriping will begin soon. See calendar of activity dates.
During this time, parking will be suspended in specific areas on East and West Drive. Work areas will be blocked off the night before and parking will be prohibited in that work zone for 48 hours to allow the sealcoating to dry and restriping to be completed. Please be mindful of the work and avoid parking in those areas. Residents will be notified on specific work zone dates based on where they live.
SCHEDULE: Work will be done in eight phases and parking will be prohibited in those specific sections of Harbor Island before and during work. There will be NO PARKING in Phase 1 starting Thursday, November 7.
Phases 1 & 2: 7946 East Drive to 7920 East Drive 11/7-9 & 11/11-13
Phases 3 & 4: 7920 East Drive to Harbor Island Parkway 11/14-16 & 11/18-20
Phases 5 & 6: Harbor Island Parkway to 7920 West Drive 11/21-23 & 11/25-27
Phases 7 & 8: 8000 West Drive to 7920 West Drive 12/2-4 & 12/5-7
Â
WHAT TO EXPECT:
-Buildings should not use sprinklers before and during sealcoating.
-Sealcoat does not fill in holes or cracks in the pavement.
-Sealcoating is susceptible to scuffing and marks until it has properly cured.
-All irrigation systems should be turned off 24 hours prior to the commencement of your project and stay off 48 hours after completion of project. The surface must dry upon our arrival to avoid premature wear of the material.
-Please suspend lawn services and/or deliveries during the work period.
-All vehicles must be removed from the work area the night before to allow work to begin by 7:15am.
Questions? Please contact NBV Public Works Director Marlon Lobban: [email protected]